Used (2) 5,000 GPD LNG Trains designed by Cryofuel Systems and built in 2001. Liquefaction done with Nitrogen Expansion Technology. Turbo Expander and Cold Box fabricated by CryoStar France S.A. Includes gas pre-treatment. Excludes power generation and LNG storage and loadout. Shut down Mid-2017.

Major Equipment

Gas Inlet Scrubber
Process Gas Chiller
Guard Beds
Gas Purification Systems (each train – Unit A & B)
Flare Gas Supply Header
Flare System
Liquefaction Systems (each train – Unit A & B)
Refrigeration Compressors (each train – Unit A & B)
Seal Gas Recovery Systems (each train– Unit A & B)
Expander Systems (each train– Unit A & B)
Nitrogen Generator
Nitrogen Distribution Systems (each train– Unit A & B)
Share
SPECIFICATIONS RESOURCES
Year Built
2001
Year Shut
2017
Capacity
(2) 5000 GPD